"That won't happen till closer to the end of the project because there's still a lot of dirt to move," Dan Erickson told the Las Vegas Review-Journal in late September. Erickson manages the 215 Beltway and Summerlin Parkway interchange rebuild. He was talking about the paths that lead up to the project's new pedestrian and bike bridges. The bridges are built. The paths are not.
That detail matters for anyone at The Ridges who uses the paved 215 Beltway Trail. A brand-new 3.5-mile trail along Summerlin Parkway is meant to join the Beltway Trail across one of those bridges. The city's trail is on track to finish in early 2027. The bridge paths are on the county's timeline, and that timeline runs into 2028.
Two Agencies, Two Clocks, One Contractor
These are two projects run by two governments.
The Summerlin Parkway Trail belongs to the City of Las Vegas. According to the city's Public Works project page, it's a $26 million, 12-foot-wide paved trail with lighting, fencing and trash receptacles. It runs between the Summerlin Interchange and Rampart Boulevard. Construction started August 18, 2025, and the page lists expected completion as Spring 2027. A city project update puts the funding at 95% federal money through the Congestion Mitigation and Air Quality program and 5% from the RTC of Southern Nevada.
The 215/Summerlin Parkway interchange belongs to Clark County. The county's project sheet lists a $130 million contract, a construction start of Monday, February 10, 2025, and an expected duration of 1,100 days. FOX5 reported in February 2026 that the completion target was March 2028. In September the Review-Journal described it more broadly as spring 2028.
Las Vegas Paving is the contractor on both. Same crews, different owners, and finish dates roughly a year apart.
What Gets Paved This Fall
The city's trail is in its final stretch. 8 News Now reported that crews started paving the section between Anasazi Drive and Town Center Drive on Tuesday, October 13, the day before its October 14 story ran. The city told the station the rest of the schedule looked like this:
- 215 to Anasazi Drive. Paving expected within about three weeks of the October 14 report, which puts it around the first week of November.
- Town Center Drive to Rampart Boulevard. Paving expected within about two months of the report, so around mid-December.
- After paving. Benches, trash cans and bike service stations get installed.
- Wrap-up. A city spokesperson said the project is still on track to finish next February.
The route changes sides partway. The Review-Journal reported that the trail runs on the north side of Summerlin Parkway from the 215 to Anasazi, then on the south side from Anasazi to Rampart, where it connects with the Bonanza Trail. It crosses Anasazi Drive, Town Center Drive and Rampart Boulevard at street level. It goes under Crestdale Lane through a new undercrossing and over the wash on a pedestrian bridge. As of mid-October, that wash bridge was still under construction. 8 News Now placed it near Rampart, right behind the Resort at Summerlin.
None of this paving affects driving on the parkway. 8 News Now noted that the work sits off the travel lanes.
Where the Two Trails Are Supposed to Meet
The west end of the new trail is where the timing problem shows up.
Clark County describes its I-215 West Beltway Trail segment as running along the west side of the freeway from Tropicana Avenue to Charleston Boulevard. The county's trail photos show it running north and south of Flamingo Road and crossing Town Center Drive on a bridge. That's the same part of Summerlin that holds The Ridges, the guard-gated hillside village built around Bear's Best. North of Charleston, the trail keeps following the beltway toward the interchange.
According to the Review-Journal's December 2025 report, the new Summerlin Parkway Trail is meant to join this path by a pedestrian bridge over the 215, which is part of the county interchange project. 8 News Now said the same in October. It reported that the Parkway trail connects to the 215 Beltway Trail "when Clark County is done with the new Summerlin Parkway Interchange."
Here's how the timeline stacks up:
- Now. The county's look-ahead for the week of October 25 lists the pedestrian and cycle trail from Far Hills Avenue to Summerlin Parkway as detoured.
- By year's end. Erickson said the last of the project's five new vehicle bridges should be finished. The three pedestrian trail bridges are already built.
- February to Spring 2027. The city finishes the Summerlin Parkway Trail.
- June 2027 to early 2028. The county's preliminary phasing plan puts the rest of the trail work in its final phase. The plan says the schedule may change.
- March to spring 2028. This is the latest reported completion for the interchange. It's also roughly when Erickson expects the bridge paths to open.
Neither government has published a date when the two trails link up for public use. Going by what the project managers have said, the city's trail will likely run from Rampart to the 215 for about a year before its western end connects to the Beltway Trail as designed. Until then, the Bonanza Trail at Rampart is the connection that should open first.
The Driving Milestone Coming First
People who drive past the construction will see a change sooner than people who walk or ride.
Erickson told the Review-Journal that the big near-term milestone is moving traffic onto the new ramp from westbound Summerlin Parkway to northbound 215. "It's going to go under that new ped bridge on the northeast corner," he said. "That should happen maybe November or December. Cars will be on the ultimate alignment."
Cars on the new ramp will pass under one of the finished pedestrian bridges, months before anyone on foot or bike can use it.
When the whole interchange opens, it will also include a flyover from southbound 215 straight onto eastbound Summerlin Parkway and a new on-ramp from eastbound Summerlin Parkway to southbound 215, according to the Review-Journal's February 2025 report.
For now, the restrictions run around the clock. The county's look-ahead for the week of October 25 lists:
- Two lanes and the shoulder closed on southbound 215 between Summerlin Parkway and Far Hills Avenue
- One lane open on westbound Summerlin Parkway from Anasazi Drive to the southbound 215 on-ramp
- One lane and the shoulder closed on the Far Hills Avenue ramps in both directions, with access to northbound 215 from Far Hills detoured
- A temporary traffic shift in both directions on the 215 between Far Hills Avenue and Lake Mead Boulevard
Erickson also told the Review-Journal that most of the remaining work is walls and bridges outside the travel lanes, and that he didn't expect major closures soon. The backup he did mention is southbound on the 215, where big trucks climb the hill from Cheyenne toward Lake Mead at about 10 mph.
Reading the Corridor From Granite Ridge Drive
From The Ridges, the 215 Beltway Trail is still the paved path closest to home, and nothing on its Flamingo or Town Center stretch is on the county's restriction list. The changes are farther north. The Far Hills to Summerlin Parkway segment is detoured. The parkway trail is getting paved this fall. In early 2027, Town Center Drive should have an at-grade crossing where the finished trail meets it at the parkway. Signage, lighting and benches should be in by the city's February target. The link at the beltway end depends on the county crews moving their last dirt.
The city lists 702.229.6276 for general questions about the trail. Clark County posts weekly interchange restrictions on its CC-215/Summerlin Parkway project page.
The Zhu Realty Group follows these corridor timelines so our sellers can describe what's finished and what's still coming accurately. If you're thinking about how the Summerlin Parkway changes fit your plans in The Ridges, request a free home valuation or schedule a listing consultation with our team.